Business to Consumer 66 Project

B2C66project

B2C66 is a mainland Chinese e-Mall site for the Chinese consumer marketing selling oversea products.

The Chinese having an overseas e-Mall will help address many consumer and seller concerns;

  • The high cost of doing business in the existing e-Mall
    • Drives up the cost of the products for the consumer
    • $50,000 to $75,000 start up costs
  • End to end shipping support.
    • Shipping suppliers
    • Good clearance in China
    • End to end tracking
  • Consumer will know that the products are coming from oversea validated business – no “copy” products.
  • Branding ownership – Seller will require band ownership (costs will include set up fees)

The technical creation of the website and control panels are very straight forward;

  • e-Commerce website running in Mainland China and Hong Kong.
  • Having the options to list in Hong Kong enables overseas products without Chinese product certification to sell directly to the consumer.
  • The integration of the B2C66 search engine between China and Hong Kong. This enables overseas products to be available in the Chinese search engine.
  • All this functionality will be control and managed by a single database.  

 

 B2C66 system

 

This part of the B2C66 implementation is straight forward.

The harder part is the supply of the end to end service to both the product supplier and end customer

  • Products listing and verification (we help to supplier in confirming the goods will have product been imported into China).
  • The shipping of goods from overseas to Chinese Customs in China.
  • Clearance of goods in China, payment of taxes and duty.
  • The delivery of the goods to the end customer.
  • Handling of returns.
  • Tracking of delivery end to end.

 

B2C66 delivery

 

Access to China is advanced in many aspect of the distribution channel. Access to china already has offices in key Chinese development areas in mainland China.

Project current status;

This is most complex of project we are currently planning.

We have allowed a year to create the systems and test end to end.

 

 

Phase

Status

System Design

Complete

System development

December 2017

System testing

March 2018

User acceptance testing

June 2018

Rollout

Aug 2018